Purpose:
- Eliminate risks to ensure 100% successful launch and serial production.
- Ensure 100% of APQP (Advanced Product Quality Planning) activities are closed including both PPAP and S-APQP.
Input from Veoneer:
- VS051 (Supplier Rating) results. (Note: All supplier factories are rated by all receiving Veoneer plants.)
- Complaint reports, if any.
Requirements:
- Supplier Launch Performance Review:
- Perform a launch and process review.
- Follow-up any specified project QCD-targets (Quality/Cost/Delivery), (e.g. production efficiency, failure rates, delivery performance, customer feed-back etc.) and implement actions for any non-conformities.
- Monitor early production containment (SQPS-412 Interim Inspection Plan) actions (if requested by Veoneer). If problems occur, define further countermeasures until problems are solved.
- SQPS-412 actions can not be terminated before written approval from Veoneer has been issued.
- Closure of APQP (Advanced Product Quality Planning):
- All open APQP issues shall be resolved and closed.
- All Lessons Learned shall be identified, documented and implemented and if requested shared with Veoneer.
- For all projects, the SQP project shall be documented and all required deliverables submitted through 'SQP IT application in APP' (see Training).
- Continuous Performance Monitoring:
- For continuous performance monitoring the supplier shall follow the VS051 requirements and set up further relevant key indicators. "General Requirements/Specific Requirements/Manufacturing Systems“.
- All VS051 and other relevant key indicators and referred action plans must be available for Veoneer review upon request.
- Note: Supplier should carefully review his VS051-results on monthly basis. If supplier can not reproduce or does not agree to the VS051-results submitted by Veoneer, Supplier should answer to Veoneer immediately by using the VS051 Dispute form.
Output from Supplier:
- Zero-defects.
- Quality performance according to specifications.
- 8D reports and action plans for any non-conforming issues.
- 100% on time deliveries.
- Closure of S-APQP by submission of above necessary deliverables to Veoneer SQ through the SQP project task 'project closure' using 'SQP IT application in VPP'.
Required Documents:
- Submission of necessary deliverables as an evidence through the SQP project task 'project closure' using 'SQP IT application in VPP'.
Reference Documents:
- AIAG-Manual APQP (Advanced Product Quality Planning).
- VS051 (Supplier Rating) / Appendix A (Supplier Rating Examples)
- VS051 Targets and Thresholds
- VS051 Dispute form
- SQPS-412 (Interim Inspection Plan) / SQPS-412 Appendix A - IIP Result Sheet
Latest revision
Date:
13/10/2020
Updated broken links.