3.2.2 Contract Review Process
Purpose:
- Contract, design and process review before serial/tool order to prevent problems, misunderstandings and to lower risks.
- Intention is to make sure the Veoneer requirements and specifications are met.
- To involve suppliers early enough to be able to introduce changes to improve QCD (Quality, Cost and Delivery). (before design freeze!)
- To agree on all technical and commercial aspects of the business.
Input from Veoneer:
- Project information from previous process steps.
- For CLD 2 and CLD 3 projects (Ref.:"SQPS-927 CLD3 GUIDELINES"), a Contract Review process is started by Veoneer and a review time plan is provided.
- Updates of drawings, specifications and standards.
- Delivery and packaging aspects, volumes, ramp-up, PPAP-requirements (Production Part Approval Process), special testing and gauging requirements (if any), VS 412 (Interim Inspection Plan).
- Veoneer or customer directed sourcing requirements, if applicable.
- Information from previous lessons learned with same or similar products and processes.
- Collaboration with supplier to resolve all feasibility and product review open issues.
Requirements:
- For all projects the supplier must ensure:
- That all feasibility and product review open issues are resolved before serial order (e.g. tool order etc.).
- That updated Team Feasibility Commitment (TFC) and impact on product cost and timing for any design change is provided, when necessary.
- Review of own and Veoneer provided lessons learned with same or similar products and processes and definition of appropriate actions.
- Identification and preparation of material-, machine-, man-power- and other requirements to support the ramp-up plan.
- Compliance with Veoneer source directed requirements, if any.
- For CLD 2 and CLD 3 projects (Ref.:"SQPS-927 CLD3 GUIDELINES"), a Contract Review process is started by Veoneer. The requirements for suppliers to actively support this process are:
- Appropriate supplier representatives participate in the review process and attend the meetings.
- Supplier prepares and provides necessary information (i.e. preliminary tool design and Process-Flow-Chart, process layout etc.) for the meetings.
- Actively support the supplier deliverables in the Contract Review Process (use the Contract Review - Template).
- Finalization and completion of Contract Review Process before serial order (e.g. tool order etc.) :
- All Contract Review open issues should be closed.
- For any open issues not closed an approved action plan, which supports the project time line shall be available.
- Both parties (Veoneer and supplier) commit, agree and sign-off the "Contract Review - Template" -document.
Output from Supplier:
- Completed Feasibility Study process: All open issues from the TFC (Concern Action Plan) are resolved before Veoneer Design Freeze and serial order.
Required Documents:
Reference Documents:
- SQPS-927 CLD3 GUIDELINES (CLD)
- VS 005 (Substance Use Restrictions)
- VS 244 (Package and Transport Label)
- VS 244 Appendices: see VSM Standards and Templates